Project Scope:
- Interior refurbishment of the Christchurch Art Gallery. Paint , Plaster , Carpentry , General labour works.

Resource supplied:
- Sub-Contractor model; Foremen, Carpenters, Painters, Plasterers, Labourers, Hammer hands, Specialised Timber Floor Restoration tradesmen

-      Value Added:
  All aspects of wall and ceiling, repairs throughout main galleries, back of house ,hallways and staircases.
Refurbishment of the galleries pilularis timber floors – over 250 m2 of flooring removed and reinstated and over  2500m2 of flooring sanded back , epoxy filled and given three polyurethane coats of finish to bring the floor back to its previous finish.
New feature walls framed and finished in existing galleries for forth coming exhibitions.

Installation of a very detailed free standing seismic framing scheme throughout the basement


 

Project Details

Client:

Fulton Hogan

Value:

$60million

Timeframe:

April 2015 - October 2016