Project Scope:
- Repairs and refurbishment of Christchurch Polytechnic’s hospitality precinct (U Block)

Challenges Faced:
- Timing - work had to begin and be completed during the Summer break while students were absent

Resource supplied:
- Sub-Contractor model; Foremen, Carpenters, Painters, Plasterers, Labourers, Hammerhands

Value Added:
- Concrete floors pulled out and replaced
- Both internal and external carpentry repairs
- Painting and plastering


 

Project Details

Client:

Pace Project Management

Value:

$1.2 million

Timeframe:

December 2014 - March 2015